Big-D Construction has updated its completion timeline of renovations and additions to the Sorensen Student Center (SC) for the rest of this year.

   

Big-D Construction has updated its completion timeline of renovations and additions to the Sorensen Student Center (SC) for the rest of this year.

  • UVU Campus Store to be completed by April 30
  • Administration and Student Health Services to be completed by June 15
  • Food Court to be completed by August 23
  • Commissary Kitchen to be completed by October 8
  • Courtyard to be completed by October 12
  • Center for Social Impact to be completed by December 1
  • Ragan Theater and Center Stage to be completed by December 14

Other campus construction updates:

The pedestrian sidewalk that connects parking lot M26 to campus (by the Woodbury School of Business) is temporarily closed due to construction on the Scott C. Keller Building. The closure will last three weeks.